TPA panels help guide Anglian Water to a wastewater upgrade

15 Jul

Temporary roadways from TPA give Anglian Water access to a WRC improvement scheme.


Portable roadways from temporary access solutions supplier TPA have helped Anglian Water pass the halfway mark in a two-pronged improvement to a wastewater recycling centre (WRC).

The WRC on Creaton Road, Hollowell, Northamptonshire, is being improved to conform with phosphorous/iron and storm volume requirements that had to be in place by March 2024. But with approved supplier TPA’s help, the project was completed two months ahead of schedule.

The storm volume requirement was met with the provision of a new 310m3 glass-coated steel tank to supplement the existing storage tanks.

Anglian Water decided to deliver the two requirements concurrently to drive efficiency from the moment go, using one design team and a single 3D model, and one project team to generate savings in site preliminaries and to minimise disturbance to neighbours.